Project: Dredging of an extension area (Cold Harbour) for the enlargement of the Gosport Marina yacht harbour, 2000
Alleen beschikbaar in Engels
The famous Yacht harbour of Camper & Nicholsons was enlarged.
The dredging of the harbour area, known as Cold Harbour was carried out with a 1.000 m³ Trailing Suction Hopper Dredger.
This small hopperdredger brought the dreged material away to the dumping area South-West of the Island of Wight, some 15 NM from the dredging spot.
Cold Harbour area was not offering much manoevring space for this small TSHD, parts of the job were done with only a few meters of free space beside the dredger.
Dredged Volume: 100.000 m³
Dredging depth: CD – 2,00 m
Dumping area: Dumping ground SW from Island of Wight